23rd Feb 2012
New Piping is Done; & Heavy Chlorination Overnight
Today around 12:00 pm the piping was completed between the buildings. The pipes are filled with super chlorinated water. Tomorrow, Friday, February 24, 2012 we will flush and sample the line. We will know Saturday if we will be off the Conserve Water Notice.
Note: we are still running on the temporary pipeline and will be until getting the all clear from the lab.
|
|
Here are a couple of photos of the Pressure Tank piping.
|
New Chlorination system is now up and running. Please bare with us for the next week or so while we adjust the level of Chlorine back to the usual level. We are running it higher than we normally do. If you are sensitive to the Chlorine you may need to do extra filtering for the next week or so.
Sorry for any inconveniences regarding this. Please feel free to ask questions if you need to.
Sincerely,
Bruce Petersilge (820-7787) and Debby Turner (820-7633)